AssetWise CONNECT Edition Help

To Update Program Priority

From time to time you might need to adjust an asset's priority, in an activity program. Priorities are defined in AssetWise Director. For more information about setting up Program priorities, see "Defining Program Priorities", in AssetWise CONNECT Edition Implementation Guide.

Follow these steps to adjust an asset's activity program priority.

  1. Open the activity program for which you want to update an asset's priority.
  2. Select the Assets tab, and then select the asset from the list.
  3. From the Actions tab, select Update program priority.
    The Update Program Priority dialog appears. For example,
  4. Select the priority from the list.
  5. When you are finished, click Save ( ).
The asset's priority is updated in the workflow.